DVV v DVW
新加坡高等法院 · [2026] SGHC 164摘要
快速理解这份材料
编辑摘要
申请人以仲裁员越权及违反程序为由,请求撤销部分终局裁决及费用裁决。
文书原文
IN THE GENERAL DIVISION OF
THE HIGH COURT OF THE REPUBLIC OF SINGAPORE
[2026] SGHC 164
Originating Application No 1149 of 2025
Between
DVV
… Applicant
And
DVW
… Respondent
Originating Application No 256 of 2026
Between
DVV
… Applicant
And
DVW
… Respondent
JUDGMENT
[Arbitration — Award — Setting aside — Ultra petita challenge]
[Arbitration — Award — Setting aside — Breach of arbitral procedure]
Version No 1: 06 Aug 2026 (11:08 hrs)
TABLE OF CONTENTS
INTRODUCTION............................................................................................1
FACTS...............................................................................................................2
THE PARTIES ...................................................................................................2
BACKGROUND TO THE DISPUTE .......................................................................2
THE SUB-CONTRACT ARBITRATION ................................................................5
THE PARTIAL FINAL AWARD...........................................................................8
THE COSTS AWARD.......................................................................................10
THE PARTIES’ CASES................................................................................11
THE PARTIES’ CASES IN SUPPORTING AFFIDAVITS AND WRITTEN
SUBMISSIONS.................................................................................................12
The applicant’s case.................................................................................12
The respondent’s case ..............................................................................15
THE PARTIES’ CASES IN ORAL SUBMISSIONS ..................................................19
The applicant’s case.................................................................................19
The respondent’s case ..............................................................................22
ISSUES TO BE DETERMINED ..................................................................24
MY ANALYSIS..............................................................................................24
THE GENERAL PRINCIPLES FOR SETTING ASIDE ..............................................24
ISSUE 1: WHETHER THE PARTIAL FINAL AWARD OUGHT TO BE SET
ASIDE ............................................................................................................25
Issue 1a: Whether the Arbitrator exceeded his jurisdiction under
s 48(1)(a)(iv) of the AA by failing to make the payment order ................25
i
Version No 1: 06 Aug 2026 (11:08 hrs)
Issue 1b: Whether the Arbitrator acted in breach of agreed
arbitral procedure under s 48(1)(a)(v) of the AA by failing to
make the payment order ...........................................................................32
ISSUE 2: WHETHER THE COSTS AWARD OUGHT TO BE SET ASIDE ..................38
CONCLUSION...............................................................................................40
ii
Version No 1: 06 Aug 2026 (11:08 hrs)
This judgment is subject to final editorial corrections approved by the
court and/or redaction pursuant to the publisher’s duty in compliance
with the law, for publication in LawNet and/or the Singapore Law
Reports.
DVV
v
DVW and another matter
[2026] SGHC 164
General Division of the High Court — Originating Application Nos 1149 of
2025 and 256 of 2026
Dedar Singh Gill J
15 May 2026
6 August 2026 Judgment reserved.
Dedar Singh Gill J:
Introduction
1 HC/OA 1149/2025 (“OA 1149”) is an application to set aside in its
entirety a partial final award (“Partial Final Award”), issued in an ad hoc
domestic arbitration between the applicant and respondent. HC/OA 256/2026
(“OA 256”) is a related application to set aside in its entirety a partial award on
costs (“Costs Award”) issued in the same arbitration. Both applications are
made pursuant to s 48(1)(a)(iv) of the Arbitration Act 2001 (2020 Rev Ed)
(“AA”), which allows an award to be set aside where it contains decisions on
matters beyond the scope of the submission to arbitration, and s 48(1)(a)(v) of
the AA, which allows an award to be set aside where the arbitral procedure was
not in accordance with the agreement of the parties. For the reasons set out
below, I dismiss both applications.
Version No 1: 06 Aug 2026 (11:08 hrs)
DVV v DVW [2026] SGHC 164
Facts
The parties
2 The applicant is a construction company incorporated in Singapore.1
3 The respondent is a foreign construction and engineering company
registered to carry on business in Singapore.2
Background to the dispute
4 By way of a joint venture agreement dated 6 July 2015 (“JVA”), the
applicant and respondent formed an unincorporated joint venture (“JV”) for the
purpose of tendering for and carrying out a construction project in Singapore
(“Project”).3 Under the JVA, the applicant holds a 30% participation share, and
the respondent holds a 70% participation share.4 Clause 3.2.1 of the JVA
provides that the parties are to share the profits and losses of the JV in proportion
to their participatio
……
基本案情
涉及分包合同仲裁,申请人对部分终局裁决和费用裁决提……
裁判要旨
裁判要旨
法院认为申请人未能证明裁决事项超出仲裁协议范围……