IN THE GENERAL DIVISION OF
THE HIGH COURT OF THE REPUBLIC OF SINGAPORE
[2026] SGHC 67
Originating Application No 1062 of 2025
Between
DSQ
… Claimant
And
DSR
… Defendant
JUDGMENT
[Arbitration] — [Award] — [Recourse against award] — [Setting aside] —
[Jurisdiction]
[Arbitration] — [Award] — [Recourse against award] — [Setting aside] —
[Whether failure to comply with pre-arbitration procedures went to
admissibility or jurisdiction]
[Arbitration] — [Award] — [Recourse against award] — [Setting aside] —
[Whether tribunal breached natural justice by depriving party of reasonable
opportunity to respond to case against it]
[Arbitration] — [Award] — [Recourse against award] — [Setting aside] —
[Infra petita challenge]
Version No 1: 31 Mar 2026 (15:50 hrs)
TABLE OF CONTENTS
INTRODUCTION............................................................................................1
JURISDICTION...............................................................................................2
OVERVIEW ......................................................................................................2
ART 16(3) OF THE MODEL LAW AND S 10(3) OF THE IAA...............................4
DO ART 16(3) OF THE MODEL LAW AND S 10(3) OF THE IAA APPLY IN
THE PRESENT CASE? ........................................................................................6
DO ART 16(3) OF THE MODEL LAW AND S 10(3) OF THE IAA HAVE
GENERAL PRECLUSIVE EFFECT? .....................................................................13
DID THE EMPLOYER WAIVE ITS JURISDICTIONAL OBJECTIONS AFTER
PO5?.............................................................................................................24
DO THE EMPLOYER’S JURISDICTIONAL OBJECTIONS GO TOWARDS
JURISDICTION OR ADMISSIBILITY? .................................................................25
DID THE TRIBUNAL CORRECTLY DECIDE THAT IT HAD JURISDICTION?...........32
Disputes 1 to 4..........................................................................................35
Disputes 5 to 6..........................................................................................39
NATURAL JUSTICE ....................................................................................44
FIRST COMPLAINT: IN RELATION TO THE CAPPED AMOUNT FOR
PROLONGATION COSTS ..................................................................................44
SECOND COMPLAINT: IN RELATION TO THE EMPLOYER’S CASE ON
REPUDIATORY BREACH UNDER APPLICABLE LEGISLATION.............................53
THIRD COMPLAINT: IN RELATION TO THE EMPLOYER’S CASE ON PRE-
CASTING OF LOCATION BOX (“LB”) FOUNDATIONS ......................................60
FOURTH COMPLAINT: IN RELATION TO THE EMPLOYER’S EVIDENCE ON
WHETHER THE CHANGES TO THE AUTO LOCATION HUTS (“ALHS”)
CONSTITUTED VARIATIONS............................................................................65
i
Version No 1: 31 Mar 2026 (15:50 hrs)
CONCLUSION...............................................................................................71
ii
Version No 1: 31 Mar 2026 (15:50 hrs)
This judgment is subject to final editorial corrections approved by the
court and/or redaction pursuant to the publisher’s duty in compliance
with the law, for publication in LawNet and/or the Singapore Law
Reports.
DSQ
v
DSR
[2026] SGHC 67
General Division of the High Court — Originating Application No 1062 of
2025
Andre Maniam J
19 February 2026
31 March 2026 Judgment reserved
Andre Maniam J:
Introduction
1 The parties were, respectively, Employer and Contractor under a design
and build contract (the “Contract”) for certain works in relation to a railway
project. Disputes arose between them, which were referred by the Contractor to
arbitration (the “Arbitration”) before a three-member tribunal (the “Tribunal”)
comprising Sir Antony Edwards-Stuart (presiding), Mr Edwin Glasgow CBE,
QC, and Mr Harish Salve QC.
2 The Arbitration culminated in an Award dated 2 April 2025, following
which the Tribunal issued a Decision and Addendum on 25 June 2025. The
Award, as revised by the Decision and Addendum, awarded a sum of money to
the Contractor.
Version No 1: 31 Mar 2026 (15:50 hrs)
DSQ v DSR [2026] SGHC 67
3 On 25 September 2025, the Employer applied to court to set aside the
Award and the Decision and Addendum on two grounds:
(a) the Tribunal lacked jurisdiction; and
(b) the Tribunal breached natural justice in relation to four aspects
of the Award.
4 I address these grounds in turn.
Jurisdiction
Overview
5 Clause 20 of the General Conditions of Contract (“GCC”) – set out
below at [97] – prescribes a procedure to be followed before a dispute is referred
to arbitration.
6 In the Arbitration, the Employer contended that the Contractor had not
followed that pre-arbitral procedure before commencing the Arbitration, and so
the Tribunal had no jurisdiction.
7 The Tribunal dealt with the Employer’s jurisdictional objections as a
preliminary question, and ruled in Procedural Order No 5 (“PO5”)1 that the pre-
arbitral procedure had been complied with, thus rejecting the Employer’s
jurisdictional object
……
基本案情
申请人DSQ请求撤销仲裁裁决,主张仲裁庭在管辖权认定、违反自然正义(……
裁判要旨
裁判要旨
法院认为雇主关于PO5未最终决定管辖权的主张与记录不符并予以驳回。……