COD v COE

新加坡高等法院 · [2022] SGHC 126
司法审查类型
撤销仲裁裁决
案号
[2022] SGHC 126
审理法院
General Division of the High Court
法院层级
高等法院
法域
新加坡
仲裁机构
—
仲裁地
新加坡
裁判日期
2022-05-25
裁判结果
—
适用规范
Arbitration Act (Cap 10, 2002 Rev Ed) s 48

摘要

快速理解这份材料

编辑摘要

申请人以仲裁员违反自然正义及既定仲裁程序为由,请求撤销仲裁裁决。

文书原文

⁠​​‌‌‌​‌‌​‌​​‌‌​‌​‌‌‌‌​‌‌​‌‌‌‌‌‌‌‌​‌​​‌​​‌‌‌‌​​‌​⁣

IN THE GENERAL DIVISION OF

THE HIGH COURT OF THE REPUBLIC OF SINGAPORE

[2022] SGHC 126

Originating Summons No 925 of 2021

Be⁠​​‌‌‌​‌‌​‌​​‌‌​‌​‌‌‌‌​‌‌​‌‌‌‌‌‌‌‌​‌​​‌​​‌‌‌‌​​‌​⁣tween

COD

… Applicant

And

COE

… Respondent

JUDGMENT

[Arbitration — Award — Recourse against award — Setting aside — Natural

just⁠​​‌‌‌​‌‌​‌​​‌‌​‌​‌‌‌‌​‌‌​‌‌‌‌‌‌‌‌​‌​​‌​​‌‌‌‌​​‌​⁣ice]

Version No 2: 25 May 2022 (12:34 hrs)

TABLE OF CONTENTS

INTRODUCTION..................................................⁠​​‌‌‌​‌‌​‌​​‌‌​‌​‌‌‌‌​‌‌​‌‌‌‌‌‌‌‌​‌​​‌​​‌‌‌‌​​‌​⁣..........................................1

FACTS........................................................................⁠​​‌‌‌​‌‌​‌​​‌‌​‌​‌‌‌‌​‌‌​‌‌‌‌‌‌‌‌​‌​​‌​​‌‌‌‌​​‌​⁣.......................................2

THE PARTIES ....................................................................⁠​​‌‌‌​‌‌​‌​​‌‌​‌​‌‌‌‌​‌‌​‌‌‌‌‌‌‌‌​‌​​‌​​‌‌‌‌​​‌​⁣...............................2

BACKGROUND TO THE DISPUTE ..............................................................⁠​​‌‌‌​‌‌​‌​​‌‌​‌​‌‌‌‌​‌‌​‌‌‌‌‌‌‌‌​‌​​‌​​‌‌‌‌​​‌​⁣.........2

PROCEDURAL HISTORY..................................................................................10

THE PART⁠​​‌‌‌​‌‌​‌​​‌‌​‌​‌‌‌‌​‌‌​‌‌‌‌‌‌‌‌​‌​​‌​​‌‌‌‌​​‌​⁣IES’ CASES................................................................................12

COD’S SUBMISSIONS ..........⁠​​‌‌‌​‌‌​‌​​‌‌​‌​‌‌‌‌​‌‌​‌‌‌‌‌‌‌‌​‌​​‌​​‌‌‌‌​​‌​⁣..........................................................................12

COE’S SUBMISSIONS ..........................⁠​​‌‌‌​‌‌​‌​​‌‌​‌​‌‌‌‌​‌‌​‌‌‌‌‌‌‌‌​‌​​‌​​‌‌‌‌​​‌​⁣...........................................................15

ISSUES TO BE DETERMINED ...................................⁠​​‌‌‌​‌‌​‌​​‌‌​‌​‌‌‌‌​‌‌​‌‌‌‌‌‌‌‌​‌​​‌​​‌‌‌‌​​‌​⁣...............................16

ISSUE 1: DID THE ARBITRATOR PROCEED CONTRARY TO

THE ARBITRAL PROCEDURE AGREED BY THE PAR⁠​​‌‌‌​‌‌​‌​​‌‌​‌​‌‌‌‌​‌‌​‌‌‌‌‌‌‌‌​‌​​‌​​‌‌‌‌​​‌​⁣TIES,

THAT IS TO HAVE ONLY ONE TRANCHE OF HEARING

WITHOUT BIFURCATION INTO LIABILITY AND

QUANTUM PHASES? ..................⁠​​‌‌‌​‌‌​‌​​‌‌​‌​‌‌‌‌​‌‌​‌‌‌‌‌‌‌‌​‌​​‌​​‌‌‌‌​​‌​⁣................................................................17

ISSUE 2: WAS COE’S CLAIM FOR DAMAGES IN LIEU OF

SPECIFI⁠​​‌‌‌​‌‌​‌​​‌‌​‌​‌‌‌‌​‌‌​‌‌‌‌‌‌‌‌​‌​​‌​​‌‌‌‌​​‌​⁣C PERFORMANCE BASED ON THE FORMULA OF

BALANCE CONTRACT PRICE LESS SCRAP VALUE

INTRODUCED ONLY AFTER THE INTERIM AWARD? ...⁠​​‌‌‌​‌‌​‌​​‌‌​‌​‌‌‌‌​‌‌​‌‌‌‌‌‌‌‌​‌​​‌​​‌‌‌‌​​‌​⁣.................20

ISSUE 3: DID THE ARBITRATOR, IN BREACH OF NATURAL

JUSTICE, ALLOW COE TO ADVANCE THIS CLAIM

WITHOUT GIVI⁠​​‌‌‌​‌‌​‌​​‌‌​‌​‌‌‌‌​‌‌​‌‌‌‌‌‌‌‌​‌​​‌​​‌‌‌‌​​‌​⁣NG COD A FAIR AND REASONABLE

OPPORTUNITY TO RESPOND? ...............................................................25

ISSUE 4: DID THE ARBITRATOR, IN BREACH OF NATURAL

JUSTICE, FAIL TO CONSIDER COD’S ARGUMENTS

DISPUTING COE’S CONTENTION THAT THERE WAS NO

AVAILABLE MARKET FOR THE CRANES?.........................................25

i

Version No 2: 25 May 2022 (12:34 hrs)

CONCLUSION...............................................................................................27

ii

Version No 2: 25 May 2022 (12:34 hrs)

This judgment is subject to final editorial corrections approved by the

court and/or redaction pursuant to the publisher’s duty in compliance

with the law, for publication in LawNet and/or the Singapore Law

Reports.

COD

v

COE

[2022] SGHC 126

General Division of the High Court — Originating Summons No 925 of 2021

Philip Jeyaretnam J

13–14 April 2022

25 May 2022 Judgment reserved.

Philip Jeyaretnam J:

Introduction

1 Arbitration, like any process for dispute resolution, is dynamic. Parties

make choices of what to emphasise and what to contest. The arbitrator must

make sense of what may be complex submissions that interlock and interact. It

is generally not wrong for an arbitrator to seek further submissions from parties

when this might help his task to adjudicate fairly and justly. Indeed, doing so

might well be considered part of doing justice in the round, rather than, as

claimed by the applicant in these proceedings, a breach of agreed procedure and

of natural justice.

Version No 2: 25 May 2022 (12:34 hrs)

COD v COE [2022] SGHC 126

Facts

The parties

2 This is an application under s 48 of the Arbitration Act

(Cap 10, 2002 Rev Ed) (the “AA”) to set aside a final award dated 21 June 2021.

The applicant, COD, is a company incorporated in Singapore. It is a shipbuilder.

The respondent, COE, is also a company incorporated in Singapore. It makes

marine and offshore equipment.1

Background to the dispute

3 COE contracted to make and deliver to COD two identical fibre rope

cranes (the “Cranes”).2 There was one contract for each crane on the same terms

(“the contracts”). Both contained an identical arbitration clause.3

4 While COD considered fibre rope cranes to be better than traditional

steel wire rope cranes because of higher buoyancy and lighter weight, such

cranes were also quite new to the market.4 The Cranes were intended to be

mounted on COD’s vessels for use in offshore operations.5

5 After the contracted delivery dates for the Cranes had passed, COD

terminated each of the contracts on the same ground, namely non-compliance

1 1st Affidavit of COD’s representative dated 10 September 2021 (“1COD1–17COD1”)

vol 1 at paras 8–9.

2 1COD1 at paras 10–11.

3 1COD1 at para 33.

4 1COD1 at para 11, Respondent’s written submissions dated 6 April 2022 (“COE WS”)

at para 18.

5 1COD1 at para 12.

2

Version No 2: 25 May 2022 (12:34 hrs)

COD v COE [2022] SGHC 126

with contractual specifications and requirements.6 COD did not take delivery.7

COE commenced two arbitrations alleging breach of contract on the basis of

wrongful refusal to take delivery of the Cranes. COE sought specific

performance and payment of the balance contract price of the Cranes, with

damages in the alternative. Pending the outcome of the proceedi

……

基本案情

⁠​​‌‌‌​‌‌​‌​​‌‌​‌​‌‌‌‌​‌‌​‌‌‌‌‌‌‌‌​‌​​‌​​‌‌‌‌​​‌​⁣COD与COE发生争议并提交仲裁。COD主张仲裁员违反了双方约定的单一阶段审理程序,且在未给予其公……

裁判要旨

裁判要旨

⁠​​‌‌‌​‌‌​‌​​‌‌​‌​‌‌‌‌​‌‌​‌‌‌‌‌‌‌‌​‌​​‌​​‌‌‌‌​​‌​⁣仲裁员为公正裁判而寻求当事人进一步陈述通常并无不当,此……

案件文书

原始文书[2022] SGHC 126.pdf上传文档解析入库

下载原始文书需登录会员账号。

会员内容

剩余 50% 正文未显示

登录后可继续阅读全文与原文段落,专业会员还可下载原始文书。
登录 / 注册查看会员方案

相似资源

10
广州市鼎泓房地产开发有限公司与中国银行股份有限公司广州番禺支行、曹晋宏申请撤销仲裁裁决一案共同争点、同类资源某甲公司与某乙公司申请撤销仲裁裁决一案共同争点、同类资源某甲公司与某乙公司申请撤销仲裁裁决一案共同争点、同类资源某甲公司与某乙公司申请撤销仲裁裁决一案共同争点、同类资源某甲公司与某乙公司申请撤销仲裁裁决一案共同争点、同类资源某甲公司与某乙公司申请撤销仲裁裁决一案共同争点、同类资源

当事人与争议

撤销仲裁裁决程序正当性

推荐引用

COD v COE,新加坡高等法院 · [2022] SGHC 126。载在一裁仲裁数据库。